Smart Metering Migration

 
 
 
 

Pelicam supports E.ON in meeting the government mandate of

installing smart meters to 6 million homes by the end of the decade

 
 
Avatar
Avatar Avatar Avatar

Major technical proving exercise preparing E.ON for roll-out of 6 million meters.

Integration between in-house legacy systems landscape, the Head End solution and meter manufacturer devices, to deliver single and dual fuel capability.

Pelicam provided specific industry expertise and major project delivery experience to help reduce the risks associated with a large-scale implementation.

 
Avatar

“The Pelicam Health Check was extremely thorough and insightful in exposing areas of the programme we may have otherwise missed.”

John Fisher, Head of Solution Development - Metering

 
Avatar
 

The Problem

The project, MIDOS, involves major elements of technical proving  whereby legacy applications are integrated through a routing engine and communications ‘Head End’ solution with SMART meters (electricity and gas). An industrial strength solution is required in order to reduce the risks associated with the roll-out to 6 million properties, maintain consumer confidence and retain a competitive edge.

The Solution

Pelicam were required to deliver a detailed health check across all aspects of the project. In particular, attention was focused on the key issues, risks and proposed remediation looking forward. 40 documents were subject to detailed scrutiny and 25 key stakeholders were interviewed. Pelicam worked collaboratively with E.ON’s senior project executive prior to the development of their own action-plan to address high priority issues. Pelicam also highlighted a number of strategic issues which E.ON faces in its quest to deliver a project of this scale.

The Result

Avatar Avatar Avatar Avatar

A more realistic plan was delivered and communicated

Single and dual fuel solutions were proven

Initial roll-out strategy was changed to concentrate on single electricity installations

E.ON is now well positioned to plan the remainder of the project in the light of lessons learnt.